Duration: 24 months Activities
Activity 1: Development of a work plan consolidating tasks with timetable for the whole project
Activity 2: Day-by-day coordination of the project (communication with partners and with EC officer(s) on behalf of the partners and reporting to EC with the contribution of project's partners)
Activity 3: Organization and coordination of one 3-day kick-off and three 3-day managerial meetings and participation in the 1-day Kick-off Seminar of Daphne III
Activity 4: Development of project's progress monitoring tools and implementing progress evaluation through project's life
Activity 5: Financial administration of the project and reporting to the EC
Activity 6: External evaluation Outputs
1. 1-day Kick off seminar
2. 3-day Kick off meeting
3. 1st 2-day MM
4. 2nd 2-day MM
5. 3rd 2-day MM
6. Implementation of progress monitoring
7. Evaluation of the project's deliverables throughout the project's life Deliverables
• Work plan (see Activity 1)
• Final technical narrative implementation report (see Activity 2)
• Meetings documentation (see Activity 3)
• Progress monitoring methodology, tools & reports (see Activity 4)
• Final financial statements (see Activity 5)
• Final External Evaluation Report